Section 3-5 - Permit Compliance

(a) Construction, installation, or modification of facilities shall be allowed only in accordance with the terms and conditions of permits issued pursuant to the Act and provisions of these regulations.

(b) No construction, installation or modification of a public water supply, sewerage system, treatment works, disposal system or other facility, excluding uranium mill tailings facilities, capable of causing or contributing to pollution shall be allowed unless a permit to construct, install or modify has been obtained from the Administrator. The permit shall be an individual permit, a general permit, or a permit by rule.

(c) The issuance of a permit to construct does not relieve the permittee of its responsibility to properly plan, design, construct, operate and maintain the facility described in the application and permit conditions.

(d) Land application or surface disposal shall be allowed only in accordance with the terms and conditions of permits issued pursuant to the Act and provisions of these regulations.

(e) Reuse of treated wastewater shall be allowed only in accordance with the terms and conditions of permits issued pursuant to the Act and provisions of these regulations.

020-3 Wyo. Code R. § 3-5