N.H. Code Admin. R. Env-Wq 708.03

Current through Register No. 25, June 20, 2024
Section Env-Wq 708.03 - Planning for Unit Process Maintenance and Dewatering Required
(a) The WWTP shall be designed to facilitate unit process maintenance such that:
(1) Each unit of the WWTP can be removed from service independently;
(2) The design facilitates WWTP operation during unit maintenance and emergency repair so as to minimize deterioration of effluent quality;
(3) Solids retention, sludge handling, and disinfection are addressed as specified in this chapter; and
(4) WWTP by-passes that allow raw or insufficiently treated sewage to be discharged directly to a water course are prevented.
(b) For WWTP upgrade or expansion, the technical specifications prepared per Env-Wq 703.02 shall include a detailed description of how to maintain existing WWTP operations, delineating the suggested construction sequence and number of units to be removed from treatment operation.
(c) A means of unit isolation and dewatering shall be provided for each process unit.
(d) Each tank shall be protected against flotation.

N.H. Code Admin. R. Env-Wq 708.03

(See Revision Note at chapter heading for Env-Wq 700) #8590, eff 3-25-06

Amended byVolume XXXIV Number 46, Filed November 13, 2014, Proposed by #10693, Effective 10/15/2014, Expires10/15/2024.