68 Ind. Admin. Code 1-8-3

Current through November 6, 2024
Section 68 IAC 1-8-3 - Submission of support facility building documents

Authority: IC 4-33-4-1; IC 4-33-4-2; IC 4-33-4-3

Affected: IC 4-33

Sec. 3.

Upon the request of the executive director, artists' renderings and architectural and engineering drawings of the support facilities shall be submitted to the executive director not less than thirty (30) days prior to the initiation of construction activities unless the drawings were approved during the application process. Support facilities shall be constructed in accordance with approved renderings and drawings submitted.

68 IAC 1-8-3

Indiana Gaming Commission; 68 IAC 1-8-3; filed Jun 23, 1995, 2:30 p.m.: 18 IR 2650; readopted filed Oct 15, 2001, 4:34 p.m.: 25 IR 898; readopted filed Sep 14, 2007, 1:40 p.m.: 20071003-IR-068070354RFA; readopted filed November 26, 2013, 3:58 p.m.: 20131225-IR-068130354RFA