4 Colo. Code Regs. § 723-3-3918

Current through Register Vol. 47, No. 11, June 10, 2024
Section 4 CCR 723-3-3918 - Coordination of Circuit Protection Equipment
(a) Prior to interconnection and at the earliest time possible after a qualifying facility provides its complete design information, but in no event later than 25 days after submission of complete design information, a utility shall provide a written statement to the qualifying facility as to whether the utility's circuit protection equipment can accommodate the equipment of the qualifying facility.
(b) A utility shall evaluate the effects of a proposed interconnection, together with the aggregate effects of all other interconnections, on the utility's installed circuit protection equipment. Costs of the evaluation shall be an interconnection cost paid by the qualifying facility.
(c) As part of normal planning, a utility shall evaluate the interaction between a qualifying facility's operations and the utility's installed circuit protection equipment. The cost of evaluation shall be an interconnection cost of the qualifying facility.
(d) If the design of a qualifying facility causes replacement or significant re-coordination of the utility's circuit protection equipment, or if the design reasonably can be expected to require extraordinary operation of the utility's installed protection equipment, the utility shall not interconnect with the qualifying facility. The utility shall decline to interconnect until either the design has been modified to eliminate the problems or specific modified designs for the interconnection are established. Replacement and re-coordination costs shall be an interconnection cost of the qualifying facility.
(e) A qualifying facility shall provide the utility with a description of the qualifying facility's electrical and mechanical equipment sufficient for the utility to determine the safety and adequacy of its installed service drops and supply equipment. The qualifying facility shall provide this information at the time it submits its design information to the utility.

4 CCR 723-3-3918

38 CR 17, September 10, 2015, effective 9/30/2015
39 CR 06, March 25, 2016, effective 4/14/2016
39 CR 08, April 25, 2016, effective 5/15/2016
40 CR 22, November 25, 2017, effective 12/15/2017
42 CR 03, February 10, 2019, effective 3/2/2019
42 CR 07, April 10, 2019, effective 4/30/2019
42 CR 09, May 10, 2019, effective 5/30/2019
43 CR 08, April 25, 2020, effective 5/15/2020
43 CR 12, June 25, 2020, effective 7/15/2020
43 CR 20, October 25, 2020, effective 11/14/2020
44 CR 13, July 10, 2021, effective 7/30/2021
44 CR 24, December 25, 2021, effective 1/14/2022
45 CR 18, September 25, 2022, effective 10/15/2022
46 CR 02, January 25, 2023, effective 2/14/2023