Neb. Rev. Stat. § 61-508

Current with changes from the 2024 legislative session enacted on or before 4/18/2024
Section 61-508 - Request for qualifications; prequalify design-builders and progressive design-builders; notice; short list
(1) The department shall prepare a request for qualifications for design-build and progressive design-build proposals and shall prequalify design-builders and progressive design-builders. The request for qualifications shall describe the project in sufficient detail to permit a design-builder or a progressive design-builder to respond. The request for qualifications shall identify the maximum number of design-builders or progressive design-builders the department will place on a short list as qualified and eligible to receive a request for proposals.
(2) A person or organization hired by the department under section 61-505 shall be ineligible to compete for a design-build contract on the same project for which the person or organization was hired.
(3) The request for qualifications shall be (a) published in a newspaper of statewide circulation at least thirty days prior to the deadline for receiving the request for qualifications and (b) sent by first-class mail to any design-builder or progressive design-builder upon request.
(4) The department shall create a short list of qualified and eligible design-builders or progressive design-builders in accordance with the guidelines adopted pursuant to section 61-506. The department shall select at least two prospective design-builders or progressive design-builders, except that if only one design-builder or progressive design-builder has responded to the request for qualifications, the department may, in its discretion, proceed or cancel the procurement. The request for proposals shall be sent only to the design-builders or progressive design-builders placed on the short list.

Neb. Rev. Stat. § 61-508

Laws 2023, LB 565,§ 8.
Added by Laws 2023, LB 565,§ 8, eff. 5/27/2023, op. 9/2/2023.