Neb. Rev. Stat. § 61-507

Current with changes from the 2024 legislative session enacted on or before 4/18/2024
Section 61-507 - Process for selecting design-builder or progressive design-builder
(1) The process for selecting a design-builder and entering into a design-build contract shall be in accordance with sections 61-508 to 61-511.
(2) Except as otherwise specifically provided in the Public Water and Natural Resources Project Contracting Act, the process for selecting a progressive design-builder and entering into a progressive design-build contract shall be in accordance with sections 61-508 to 61-511.

Neb. Rev. Stat. § 61-507

Laws 2023, LB 565,§ 7.
Added by Laws 2023, LB 565,§ 7, eff. 5/27/2023, op. 9/2/2023.