041-7 Wyo. Code R. § 7-2

Current through April 27, 2019
Section 7-2 - Inspections

(a) Requested electrical inspections shall be made within five (5) business days of the request by the electrical contractor, the general contractor, or the owner. Unless previous arrangements have been made, the person requesting the inspection shall pay for the inspection.

(b) Electrical inspections may be made for any electrical wiring permit issued. These inspections may be made at any time during construction, or within thirty (30) days after completion of the installation for which an electrical wiring permit or plan review was performed.

(c) When serious or hazardous conditions are discovered upon inspection, the permittee shall be notified by letter, sent by certified mail return receipt requested or by regular mail with delivery confirmation service requested, which details the serious or hazardous conditions. A copy of the inspection report shall also be attached. The utility shall be copied with the same letter and report sent by certified mail return receipt requested or by regular mail with delivery confirmation service requested.

(d) Electrical permits for temporary power will be issued for a period of ninety (90) days as set forth in Article 305 of The National Electrical Code, unless the permittee requests a longer duration. An electrical wiring permit is required for a temporary service.

041-7 Wyo. Code R. § 7-2