W. Va. Code R. § 38-4-30

Current through Register Vol. XLI, No. 37, September 13, 2024
Section 38-4-30 - Reporting Requirements
30.1. Monthly progress reports during construction: A written report containing the results of each inspection of construction progress shall be submitted to the Secretary every month while the dam and its appurtenances are under construction. The report shall include, but not be limited to, specific instrumentation readings, test results, freeboard, crest elevation, and specific construction or quality control problems with documentation of implemented solutions. The report on the drainage system and protective filters shall include color photographs taken during and after construction, but before underdrains are covered with material. If the underdrain system is constructed in phases, each phrase shall be certified separately.
30.2. Post construction inspection report: A report shall be submitted to the Secretary by the dam owner reporting the findings of the final construction inspection required under Section 27 of these rules. Certification by an engineer shall be submitted to the Secretary with the inspection report to verify that the dam and its appurtenances were constructed in substantial conformance with the approved plans and specifications and that the dam and its appurtenances are functioning as designed.
30.3. Inspection reports for dams with serious problems: A written report containing the observations of each inspection required shall be submitted to the Secretary by the dam owner within thirty (30) days of the inspection.

W. Va. Code R. § 38-4-30