Current through Register Vol. XLI, No. 45, November 8, 2024
Section 157-14-5 - Bidder's responsibility5.1. The submitting contractor must carefully examine the plans, specifications, special provisions, contract forms and the work site. When the contractor submits a bid, they are asserting they have made such examinations and agree with the character, quality, and quantity of work to be performed.5.2. The contractor acknowledges the quantities shown on the plans and the schedule of items are only estimates, and that increases or decreases to the quantities are possible. The contractor further agrees to accept the unit prices for the work performed and accepted, unless otherwise provided for in the contract. The Division will make every effort to provide sufficient information to the bidders. The contractor must carefully follow and comply with all instructions for submitting a bid or they risk having their bid rejected. W. Va. Code R. § 157-14-5