Wash. Admin. Code § 480-108-120

Current through Register Vol. 24-21, November 1, 2024
Section 480-108-120 - Cumulative effects of interconnections

Electrical companies will evaluate on an ongoing basis, but not less than once every five years, the cumulative effect, including benefits to its other customers, of interconnections made under Part 2 of this chapter on its electric system and will retain appropriate records of its evaluations.

Wash. Admin. Code § 480-108-120

Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-120, filed 9/27/07, effective 10/28/07.