Wash. Admin. Code § 480-108-015

Current through Register Vol. 25-01, January 1, 2025
Section 480-108-015 - Scope of Part 1

The provisions in Part 1 of this chapter apply to interconnections, and to applications to interconnect, customer-owned generating facilities with a nameplate capacity rating of 300 kW or less to an electrical company's electrical system under this chapter.

Wash. Admin. Code § 480-108-015

Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 07-20-059 (Docket UE-060649, General Order 545), § 480-108-015, filed 9/27/07, effective 10/28/07.