Wash. Admin. Code § 296-104-515

Current through Register Vol. 24-21, November 1, 2024
Section 296-104-515 - Repairs - Do riveted repairs to boilers and unfired pressure vessels require prior approval?

Yes, riveted repairs to boilers and unfired pressure vessels requires prior approval by the chief inspector.

Wash. Admin. Code § 296-104-515

Statutory Authority: RCW 70.79.030, 70.79.040, 70.79.150, 70.79.290, 70.79.330, 70.79.350, and chapter 70.79 RCW. 04-01-194, § 296-104-515, filed 12/24/03, effective 1/24/04. Statutory Authority: RCW 70.79.030 and 70.79.040. 98-22-024, § 296-104-515, filed 10/28/98, effective 11/28/98. Statutory Authority: RCW 70.79.030. 86-04-059 (Order 86-01), § 296-104-515, filed 2/4/86. Statutory Authority: RCW 70.79.030 and 70.79.330. 84-21-012 (Order 84-20), § 296-104-515, filed 10/5/84; Part VII, § 4, filed 3/23/60.