Utah Admin. Code 23-1-614

Current through Bulletin No. 2024-21, November 1, 2024
Section R23-1-614 - Subcontractor Lists

The division may not consider, or award to, any bid submitted by a bidder if the bidder fails to submit a subcontractor list meeting the requirements of Section 63A-5b-605 and this rule. For purposes of Section R23-1-614, the definitions of Section 63A-5b-605 shall be applicable. Within 24 hours after the bid opening time, not including Saturdays, Sundays, and state holidays, the apparent lowest three bidders, as well as other bidders that desire to be considered, shall submit to the division a list of their first-tier subcontractors that are over the dollar amounts stated in Subsection 63A-5b-605(3)(a)(ii).

(1) The subcontractor list shall include the following:
(a) the type of work the subcontractor is to perform;
(b) the subcontractor's name;
(c) the subcontractor's bid amount;
(d) the license number of the subcontractor issued by the Utah Division of Professional Licensing, if such license is required under Utah law; and
(e) the impact that the selection of any alternate included in the solicitation would have on the information required by Section R23-1-614.
(2) The contract documents for a specific project may require that additional information be provided regarding any contractor, subcontractor, or supplier.
(3) If pursuant to Subsection 63A-5b-605(7), a bidder intends to perform the work of a subcontractor or get at a later date, a bid from a qualified subcontractor, the bidder shall:
(a) comply with the requirements of Section 63A-5b-605 and
(b) clearly list the bidder on the subcontractor list form.
(4) Errors on the subcontractor list will not disqualify the bidder if the bidder can demonstrate that the error is a result of the bidder's reasonable reliance on information that was provided by the subcontractor and was used to meet the requirements of this rule, and, provided that this does not result in an adjustment to the bidder's contract amount.
(5) Pursuant to Sections 63A-5b-605 and 63G-2-305, information contained in the subcontractor list submitted to the division shall be classified public except for the amount of subcontractor bids which shall be classified as protected until a contract has been awarded to the bidder at which time the subcontractor bid amounts shall be classified as public. During the time that the subcontractor bids are classified protected, they may only be made available to procurement and other officials involved with the review and approval of bids.
(6) Change of Listed Subcontractors. 24 hours after the bid opening, the contractor may change the contractor's listed subcontractors only after receiving written permission from the director based on complying with all the following:
(a) The contractor has established in writing that the change is in the best interest of the state and that the contractor establishes an appropriate reason for the change, which may include the following reasons:
(i) the original subcontractor has failed to perform, or is not qualified or capable of performing; or
(ii) the subcontractor has requested in writing to be released.
(b) The circumstances related to the request for the change do not show any bad faith in the original listing of the subcontractors.
(c) The contractor shall comply with any requirement set forth by the director to ensure that the process used to select a new subcontractor does not give rise to bid shopping.
(d) Any increase in the cost of the subject subcontractor work shall be borne by the contractor.
(e) Any decrease in the cost of the subject subcontractor work shall result in a deductive change order being issued for the contract for such decreased amount.

Utah Admin. Code R23-1-614

Adopted by Utah State Bulletin Number 2015-7, effective 3/3/2015
Amended by Utah State Bulletin Number 2022-06, effective 2/24/2022
Amended by Utah State Bulletin Number 2023-04, effective 2/8/2023