S.D. Admin. R. 74:36:07:129

Current through Register Vol. 50, page 162, June 24, 2024
Section 74:36:07:129 - Existing municipal solid waste landfill corrective action and timeline notifications

The owner or operator of an existing municipal solid waste landfill that meets the requirements of § 74:36:07:105 shall submit the following:

1. For corrective action required according to subdivision 74:36:07:112(3)(c) or (4)(c) and expected to take longer than 120 days after the initial exceedance to complete, the owner or operator shall submit the root cause analysis, corrective action analysis, and corresponding implementation timeline to the Secretary as soon as practicable but no later than 75 days after the first measurement of positive pressure or temperature monitoring value of 55 degrees Celsius (131 degrees Fahrenheit) or above. The Secretary shall approve the plan for corrective action and the corresponding timeline; and
2. For corrective action required according to subdivision 74:36:07:112(3)(c) or (4)(c) and is not completed within 60 days after the initial exceedance, the owner or operator shall submit a notification to the Secretary as soon as practicable but no later than 75 days after the first measurement of positive pressure or temperature exceedance.

S.D. Admin. R. 74:36:07:129

46 SDR 064, effective 11/25/2019

General Authority: SDCL 34A-1-6.

Law Implemented: SDCL 34A-1-18.