Current through Register Vol. 51, page 57, November 12, 2024
Section 74:36:05:35 - Requirements for minor permit amendmentsA minor permit amendment is an amendment to an existing permit and is issued by the secretary. A minor permit amendment may be issued by the secretary if the proposed revision meets the following requirements:
(1) It does not violate any applicable requirement;(2) It does not involve significant changes to existing monitoring, reporting, or record keeping requirements in the permit;(3) It does not require or change a case-by-case determination of an emission limit or other standard, a source-specific determination for temporary sources of ambient impacts, or a visibility or increment analysis;(4) It does not seek to establish or change a permit term or condition for which there is no corresponding underlying applicable requirement that the source has assumed to avoid an applicable requirement, a federally enforceable emissions cap assumed to avoid classification as a modification under any provision of Title I, and an alternative emissions limit approved pursuant to regulations promulgated under § 112(i)(5) of the Clean Air Act; and(5) It does not constitute a modification under Title I of the Clean Air Act.S.D. Admin. R. 74:36:05:35
19 SDR 157, effective 4/22/1993; 21 SDR 119, effective 1/5/1995.General Authority: SDCL 34A-1-6, 34A-1-21.
Law Implemented: SDCL 34A-1-21.