Section 20:10:36:50 - Tier 4 interconnection

The public utility shall use the tier 4 interconnection review procedures for an application that does not qualify for tier 1, tier 2, or tier 3 review and for which the small generator facility has an electric nameplate capacity that is ten megawatts or less. The public utility may not impose additional requirements.