The public utility shall use the tier 4 interconnection review procedures for an application that does not qualify for tier 1, tier 2, or tier 3 review and for which the small generator facility has an electric nameplate capacity that is ten megawatts or less. The public utility may not impose additional requirements.
S.D. Admin. R. 20:10:36:50
General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.