S.D. Admin. R. 20:10:36:49

Current through Register Vol. 50, page 159, June 17, 2024
Section 20:10:36:49 - Tier 3 interconnection completion

The tier 3 application process is complete when:

(1) All tier 3 screening criteria are satisfied and any minor modifications to the EDS that may have been identified are implemented;
(2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection;
(3) There is a successful completion of the witness test, if required;
(4) The parties execute a certificate of completion; and
(5) An interconnection agreement has been executed.

S.D. Admin. R. 20:10:36:49

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.