Section 250-RICR-120-05-19.9 - Compliance Schedule
A. The owner or operator of an existing coating operation that meets any of the applicability thresholds in §§ 19.6.1 through 19.6.8 of this Part shall achieve compliance with the applicable emission limitations in § 19.7 of this Part or, if applicable, apply to the Director for an exemption under § 19.6.9(C) of this Part or apply for alternative RACT under § 19.7.9 of this Part, by July 1, 2020.
B. The owner or operator of an existing coating operation that does not meet any of the applicability thresholds in §§ 19.6.1 through 19.6.8 of this Part, as of the effective date of this regulation, shall achieve compliance with the applicable emissions limitations in § 19.7 of this Part or, if applicable, apply to the Director for an exemption under § 19.6.9(C) of this Part or apply for alternative RACT under § 19.7.9 of this Part, within one year of becoming subject to any of the applicability thresholds in §§ 19.6.1 through 19.6.8 of this Part.
C The owner or operator of any coating facility for which construction commenced on or after the July 1, 2020, that expects to meet or exceed any of the applicability thresholds in §§ 19.6.1 through 19.6.8 of this Part shall be in compliance with the applicable emissions limitations in § 19.7 of this Part upon commencing operation.
D. The compliance schedule shall not allow a coating facility to supersede any applicable emission limitations including but not limited to:
1. Best Available Control Technology determinations, or,
2. Lowest Achievable Emissions Rate determinations, or,
3. Federal New Source Performance Standards, or National Emission Standards of Hazardous Air Pollutants, or,
4. Any other condition or standard that is specifically required by the Clean Air Act (as amended) for new or modified sources.

250 R.I. Code R. 250-RICR-120-05-19.9

Amended effective 8/14/2019