Okla. Admin. Code § 252:515-21-112

Current through Vol. 41, No. 19, June 17, 2024
Section 252:515-21-112 - Eligibility requirements
(a)Use of proper tires. Only used tires obtained from tire dumps identified on the PCL or from community-wide cleanup events in the State of Oklahoma and used in accordance with the approved plans shall be eligible for compensation.
(b)Project completion report. Upon completion of the project, the governmental entity shall submit a project completion report signed and stamped or sealed by a professional engineer licensed in the State of Oklahoma, certifying the project was completed in accordance with the approved plans. The report shall include the following:
(1) the name, address and telephone number of the applicant and the certifying engineer;
(2) the tire dump from which tires came, if any, and DEQ identification number;
(3) identification of the community-wide cleanup event from which tires came, if any;
(4) quantity of tires removed from the tire dump or community-wide cleanup event, by tire type;
(5) location of the approved project;
(6) quantity and type of tires delivered to and installed in the project;
(7) documentation to verify compliance with (c) of this Section, if applicable; and
(8) other information required by DEQ.
(c)Proper disposal. Any used tires or bales not needed for the project shall be disposed at a permitted used tire processing or other used tire recycling facility, or a permitted solid waste disposal facility.
(d)DEQ inspection. After submittal of the project completion report, DEQ shall inspect the project and the project file to determine compliance with the Act, the rules in this Subchapter, and project plans.
(e)Project complete. If the project is complete, DEQ shall provide written notification, with copies to the OTC.
(f)Project incomplete. If any aspect of the project is not complete, DEQ shall give written notification of the deficiencies to the governmental entity, who shall respond accordingly. DEQ shall not authorize partial compensation for incomplete projects.
(g)Recordkeeping. Records required by this Part shall be maintained by the governmental entity for a period of three years after completion of the project.

Okla. Admin. Code § 252:515-21-112

Added at 20 Ok Reg 1151, eff 6-1-03; Amended at 29 Ok Reg 1005, eff 7-1-12