Section 252:515-21-111 - Project construction requirements
(a)Plan required. Units of local or county government in Oklahoma who will seek reimbursement from the Fund for use of baled used tires in engineering projects shall have a DEQ approved plan describing the nature of the proposed project. Such plan shall include:
(1) the location at which used tire baling operations will be performed;
(2) a description of the engineering project for which the baled tires will be used;
(3) the approximate date construction will begin and the estimated time to complete the project;
(4) plans for aesthetic enhancement in accordance with OAC 252:515-3-37;
(5) engineering designs that are signed and stamped or sealed by a professional engineer licensed in the State of Oklahoma;
(6) documentation that the project has been approved by:
(A) the unit of local government for projects sponsored by a local government; or
(B) the Board of Commissioners for the county in which the project will be located for projects sponsored by a unit of county government; and
(7) a description of how compliance with the eligibility requirements of OAC 252:515-21-112 will be achieved.
(b)DEQ review. After review, DEQ may require alterations to the plan prior to construction.
(c)Initiation of construction. Construction of the project shall not begin until the plan has been approved by DEQ.
(d)Bale storage. No more than 50 used tire bales shall be accumulated prior to beginning construction of the project.
(e)Recordkeeping. All records related to the project and required by this Section shall be maintained by the governmental entity for a period of at least three years after completion of the project.

Okla. Admin. Code § 252:515-21-111

Added at 20 Ok Reg 1151, eff 6-1-03; Amended at 29 Ok Reg 1005, eff 7-1-12