Section 252:515-11-56 - Notification of installation
(a)QA certification required. Installation of the FML shall not begin until the QA officer certifies that all required reconstructed clay liner tests have been completed for the area on which the FML is to be laid.
(b)DEQ notification required. The DEQ shall be notified at least 48 hours before installation of the FML.

Okla. Admin. Code § 252:515-11-56

Added at 20 Ok Reg 1151, eff 6-1-03