N.D. Admin. Code 43-02-13-23

Current through Supplement No. 394, October, 2024
Section 43-02-13-23 - Reclamation of exploration test wells

The plugging and reclamation of exploration test wells must comply with all applicable rules in chapter 43-02-03, including plugging and site reclamation. The commission may require the well bore to be filled with concrete or another approved plugging material from the base of the hole to the ground surface.

All lands disturbed during exploration must be reclaimed to a condition consistent with prior land use and productive capacity.

N.D. Admin Code 43-02-13-23

Adopted by Administrative Rules Supplement 2020-378, October 2020, effective 10/1/2020.

General Authority: NDCC 38-23-03

Law Implemented: NDCC 38-23-03