N.D. Admin. Code 43-02-02.4-21

Current through Supplement No. 394, October, 2024
Section 43-02-02.4-21 - Notice of mechanical integrity testing

At least thirty days before a regularly scheduled test, an operator shall notify the director of the date and approximate time of the test. The notification shall include a copy of the proposed test procedure, including procedures for wireline logging. Mechanical integrity testing shall not be conducted until an operator has received approval of the test procedure from the director. Mechanical integrity testing may be witnessed by the director.

N.D. Admin Code 43-02-02.4-21

Effective July 1, 2013.

General Authority: NDCC 38-12-02

Law Implemented: NDCC 38-12-02