Section 33-24-08-25 - Periodic testing of spill prevention equipment and containment sumps used for interstitial monitoring of piping and periodic inspection of overfill prevention equipment
1. Owners and operators of underground storage tank systems with spill and overfill prevention equipment and containment sumps used for interstitial monitoring of piping must meet these requirements to ensure the equipment is operating properly and will prevent releases to the environment:
a. Spill prevention equipment, such as a catchment basin, spill bucket, or other spill containment device, and containment sumps used for interstitial monitoring of piping must prevent releases to the environment by meeting one of the following:
(1) The equipment is double walled and the integrity of both walls is periodically monitored at a frequency not less than the frequency of the walkthrough inspections described in section 33-24-08-26. Owners and operators shall begin fulfilling paragraph 2 of subdivision a of subsection 1 and conduct a test within thirty days of discontinuing periodic monitoring of this equipment; or
(2) The spill prevention equipment and containment sumps used for interstitial monitoring of piping are tested at least once every three years to ensure the equipment is liquid tight by using vacuum, pressure, or liquid testing in accordance with one of the following criteria:
(a) Requirements developed by the manufacturer;

(NOTE: Owners and operators may use this option only if the manufacturer has developed requirements.)

(b) Code of practice developed by a nationally recognized association or independent testing laboratory; or
(c) Requirements determined by the department to be no less protective of human health and the environment than the requirements listed in subparagraphs a and b of paragraph 2 of subdivision a of subsection 1.
b. Overfill prevention equipment must be inspected at least once every three years. At a minimum, the inspection must ensure that overfill prevention equipment is set to activate at the correct level specified in subsection 3 of section 33-24-08-10 and will activate when a regulated substance reaches that level. Inspections must be conducted in accordance with one of the criteria in subparagraphs a through c of paragraph 2 of subdivision a of subsection 1.
2. Owners and operators must begin meeting these requirements as follows:
a. For underground storage tank systems in use on or before April 1, 2018, the initial spill prevention equipment test, containment sump test, and overfill prevention equipment inspection must be conducted not later than April 1, 2021.
b. For underground storage tank systems brought into use after April 1, 2018, these requirements apply at installation.
3. Owners and operators must maintain records as follows, in accordance with section 33-24-08-24, for spill prevention equipment, containment sumps used for interstitial monitoring of piping, and overfill prevention equipment:
a. All records of testing or inspection must be maintained for three years; and
b. For spill prevention equipment and containment sumps used for interstitial monitoring of piping not tested every three years, documentation showing that the prevention equipment is double walled and the integrity of both walls is periodically monitored must be maintained for as long as the equipment is periodically monitored.

(NOTE: To paragraph 2 of subdivision a of subsection 1 and subdivision b of subsection 1 the following code of practice may be used to comply with paragraph 2 of subdivision a of subsection 1 and subdivision b of subsection 1: Petroleum Equipment Institute Publication RP1200, "Recommended Practices for the Testing and Verification of Spill, Overfill, Leak Detection and Secondary Containment Equipment at UST Facilities".)

N.D. Admin Code 33-24-08-25

Amended by Administrative Rules Supplement 368, April 2018, effective 4/1/2018.

General Authority: NDCC 23-20.3-03, 23-20.3-04.1