Current through Register Vol. 36, No. 1, January 14, 2025
Section 17.9.568.20 - INTERCONNECTION AGREEMENTA. For simplified process interconnection projects, the applicant will sign a form interconnection agreement at the time it submits its interconnection application, and the utility will return a counter-signed interconnection agreement with the screen results.B. For fast track and detailed study interconnection projects: after receiving an interconnection agreement from the utility, the applicant shall have 30 business days or another mutually agreeable timeframe to sign and return the interconnection agreement. If the applicant does not sign the interconnection agreement within 30 business days, the interconnection application shall be deemed withdrawn. After the interconnection agreement is signed by the parties, the interconnection of the generating facility shall proceed under the provisions of the interconnection agreement.N.M. Admin. Code § 17.9.568.20
Adopted by New Mexico Register, Volume XXXIV, Issue 03, February 14, 2023, eff. 2/14/2023