N.J. Admin. Code § 19:2-9.3

Current through Register Vol. 56, No. 12, June 17, 2024
Section 19:2-9.3 - Fee schedule
(a) The following fee schedule is established to offset costs associated with the effects of work on roadway useful life and the review, administration, inspection, and other necessary tasks performed by Authority staff. The fee schedule shall be established as follows:
1. An application fee of $ 250.00 shall be submitted along with the completed access or occupancy permit application and other associated documents. This fee shall be non-refundable whether the Authority issues or denies the requested permit.
2. A nonrefundable permit fee of five percent of the total amount of construction or work to be performed on the Expressway or Authority property or $ 500.00, whichever is greater, plus any needed specialized fee as described in (a)3 below. The permit fee shall be paid prior to permit issuance.
3. Nonrefundable specialized fees are required as follows:
i. Shoulder closure--$ 250.00 per location per day;
ii. Lane closure--$ 500.00 per lane per location per day; and
iii. Slow downs--$ 75.00 per set-up.
(b) Fees for all other items of specialized work shall be determined by the Director of Engineering on a case-by-case basis. Such determination shall be based upon the amount of staff time and services provided.
1. All specialized fees shall be considered part of the permit fee, and shall be paid with the permit fee.
2. Specialized fees do not include services or equipment provided by the Authority.

N.J. Admin. Code § 19:2-9.3

Amended by 46 N.J.R. 879(a), effective 5/19/2014.