If a design-build contract is procured as a GMP contract, the design-builder shall be responsible for cost overruns in excess of the GMP, as properly adjusted, pursuant to the terms of the design-build contract. If the design-builder's cost of work and fee are less than the GMP as properly adjusted, the cost savings shall accrue to the Authority, but may be shared by the design-builder and the Authority in accordance with the terms of the design-build contract.