N.J. Admin. Code § 19:36-8.1

Current through Register Vol. 56, No. 12, June 17, 2024
Section 19:36-8.1 - Design and construction
(a) The design-builder shall employ or contract with the architect of record and shall be responsible for the technical integrity of final project design, constructability, extensions of the design, and operability and maintainability, pursuant to the design-build information package and/or in the design-build contract.
(b) The role of the design-builder may include, but need not be limited to, the management and control of quality, cost and the integrated schedule for design, permit applications, material and equipment acquisition, construction, training for operation and maintenance, inspection and close out of the school facilities project.
(c) The Authority's review and acceptance of interim design submissions and/or construction documents is for the purpose of mutually establishing a conformed set of contract documents compatible with the requirements of the work. Neither the Authority's nor the construction manager's review and acceptance of interim design submissions or construction documents shall be deemed to transfer design liability from the design-builder to the Authority.
(d) Once the plans and specifications are complete, and have been accepted by the Authority, the design-builder shall submit the completed plans and specifications for the school facilities project to the Department for approval of final educational adequacy, pursuant to 6A:26-5.4. Upon the approval of the plans and specifications by the Commissioner, the design-builder shall submit them to the DCA for review and approval in accordance with 5:23-4.2 4.

N.J. Admin. Code § 19:36-8.1

Amended by R.2013 d.053, effective 4/1/2013.
See: 44 N.J.R. 1318(a), 45 N.J.R. 752(a).
In (c), substituted "acceptance" for "approval" twice; and in (d), substituted "Once the plans and specifications are complete, and have been accepted by the Authority, the" for "The".