Current through Register Vol. 57, No. 1, January 6, 2025
Section 16:41F-6.3 - Plan review and approval(a) The Bureau of Landscape Architecture and Environmental Solutions (BLAES) review of a proposed VCM Plan shall not begin until all materials listed in N.J.A.C. 16:41F-6.1(b) have been received.(b) The Operations Permit Office review of the highway occupancy permit application shall not begin until all permit application information and the permit application fee have been received.(c) The BLAES and the Operations Permit Office will concurrently review the proposed VCM Plan and the highway occupancy permit application and, within 45 days of application submission, advise the applicant if the submission is deemed complete.(d) Within 45 days of the submission being deemed complete, the applicant shall be advised if the proposed VCM Plan is approved, if it must be modified, or if it is rejected and the reasons for the rejection.(e) The highway occupancy permit that will govern the VCM Plan shall not be issued until the proposed VCM Plan is approved by the BLAES.N.J. Admin. Code § 16:41F-6.3
Adopted by 47 N.J.R. 1982(a), effective 8/3/2015