N.H. Code Admin. R. Puc 206.03

Current through Register No. 25, June 20, 2024
Section Puc 206.03 - Commission Shall Initiate
(a) The commission shall initiate a proceeding to establish an alternative form of regulation if it finds that alternative regulation is likely to promote or enhance one or more of the following:
(1) Competition;
(2) Advancements in development of infrastructure;
(3) Investment in new technology, plant, and equipment;
(4) Reduction in prices; or
(5) Efficiency in services.
(b) When the commission initiates a proceeding to establish an alternative form of regulation, it shall issue an order directing the affected utility to submit detailed information consistent with the requirements of Puc 206.05 and any additional information required by Puc 206.06.

N.H. Code Admin. R. Puc 206.03

#6444, eff 1-28-97; ss by #8276, eff 1-27-05; ss by #10306, eff 4-9-13

Amended by Number 45, Filed November 9, 2023, Proposed by #13780, Effective 10/18/2023, Expires 10/18/2033.