N.H. Admin. Code § Env-Wt 511.07

Current through Register No. 45, November 7, 2024
Section Env-Wt 511.07 - Beach Replenishment Project Classifications
(a) Replenishment of sand on an existing beach shall be a minimum impact project only if all of the following criteria are met:
(1) The beach is an existing legal structure as defined in Env-Wt 102;
(2) No sand is placed below the normal high water line or limits of flowage rights, as applicable;
(3) No work is done in a wetland, watercourse, or PRA, except as provided in Env-Wt 407;
(4) No more than 10 CY of sand is used; and
(5) The beach is not replenished more frequently than once in any 6-year period.
(b) Replenishment of a beach shall be a minor impact project if the project meets the criteria in (a)(1)-(3), above, and either:
(1) The beach is replenished more frequently than once in a 6-year period; or
(2) More than 10 CY of sand but not more than 20 CY of sand will be used.
(c) Replenishment of an existing legal beach shall be a major impact project if the project does not meet the criteria specified in (a) or (b), above.
(d) A beach that is not an existing legal structure shall not be replenished unless an after-the-fact permit is obtained for construction of the beach, which shall be classified as provided in Env-Wt 511.06.

N.H. Admin. Code § Env-Wt 511.07

Derived from Volume XXXIX Number 28, Filed July 11, 2019, Proposed by #12805, Effective 12/15/2019, Expires 12/15/2029 (See Revision Notes #1 and #2 at chapter heading for Env-Wt 500).
Amended by Volume XL Number 41, Filed October 8, 2020, Proposed by #13124 Effective 10/23/2020, Expires 10/23/2030.
Amended by Number 45, Filed November 9, 2023, Proposed by #13776, Effective 10/13/2023, Expires 10/13/2033.