N.H. Code Admin. R. Env-Wq 717.04

Current through Register No. 25, June 20, 2024
Section Env-Wq 717.04 - I/A Technology Pilot Requirements
(a) A pilot test plan shall include:
(1) A description of proposed pilot unit equipment description and capacity, either as:
a.Existing treatment units parallel to the existing treatment process; or
b.A stand-alone pilot;
(2) A proposed schedule and duration, including:
a.A calendar schedule with considerations for:
1.Seasonal temperature variations relative to impact on process performance;
2.Seasonal flow variations; and
3.Seasonal waste characterization variations; and
b.Pilot duration and justification for proposed duration to account for seasonal variations;
(3) Wastewater feed characterization, including:
a.Historical WWTP flow and waste characteristic data review;
b.Proposed program for pilot wastewater characterization;
c.Wastewater sampling and analysis plan; and
d.Pretreatment requirements for the pilot equipment, if necessary;
(4) Proposed pilot equipment configuration and set up, including:
a.Pilot feed equipment and feed rate;
b.Pilot unit description and proposed location on WWTP site;
c.Flow measurement during pilot testing;
d.Pilot control methodology;
e.Sample collection and analysis plan during pilot testing; and
f.Proposed modifications to the existing facility, if required;
(5) Pilot start up plan, including:
a.Written description of pilot start up plan;
b.Startup monitoring and supervision; and
c.Proposed process stabilization determination methodology; and
(6) Field procedures and monitoring, including:
a.List of parameters to be monitored;
b.Sampling frequency and analysis for each parameter;
c.Type of sampling, grab or flow-proportional composite;
d.Sample handling procedures used to assure quality assurance; and
e.Procedures to address unusual events such as process upsets and equipment failures.
(b) A pilot test summary report shall be completed and submitted for review and approval by the department within 60 days of pilot test conclusion and prior to designing or constructing a full-scale system.
(c) The pilot test summary report shall include, at a minimum:
(1) Executive summary;
(2) Pilot methodology;
(3) Sampling and analysis methodologies;
(4) Test procedures and methods;
(5) Complete data summary;
(6) Data analysis methodology;
(7) Analysis of pilot performance; and
(8) Conclusions and recommendations.

N.H. Code Admin. R. Env-Wq 717.04

Adopted byVolume XXXIV Number 46, Filed November 13, 2014, Proposed by #10693, Effective 10/15/2014, Expires10/15/2024.