N.H. Admin. Code § Env-Wq 1205.06

Current through Register No. 44, October 31, 2024
Section Env-Wq 1205.06 - Change in Discharge
(a) An SIU proposing a new discharge or a change in quantity of its existing discharge shall obtain a new discharge permit application from the community in which the discharge is proposed and submit the completed application to the WRBP at least 60 days prior to the commencement of such discharge.
(b) If the new or modified/increased discharge requires the construction and installation of additional treatment devices, the SIU shall submit to the WRBP plans and specifications of the proposed pretreatment facility stamped by a professional engineer licensed to practice in the state of New Hampshire.
(c) An SIU proposing a change in quality of its existing discharge shall obtain a new discharge permit application from the WRBP and submit the completed application at least 60 days prior to the commencement of such modified discharge.
(d) In accordance with the criteria outlined in Env-Wq 1205.07 below, and upon approval of the discharge permit application by the WRBP pursuant to these rules and the department's industrial pretreatment program pursuant to RSA 485-A:5 and Env-Wq 305, the WRBP shall issue an amended IDP.

N.H. Admin. Code § Env-Wq 1205.06

#2707, eff 5-15-84, EXPIRED: 5-15-90

New. #4845, eff 6-20-90, EXPIRED: 6-20-96

New. #6304, eff 7-26-96; ss by #8124, INTERIM, eff 7-26-04, EXPIRES: 1-22-05; ss by #8235, eff 12-22-04 (See Revision Note at chapter heading for Env-Wq 1200) (formerly Env-Ws 1205.06); ss by #9798-A, eff 10-9-10

Amended by Volume XXXIX Number 16, Filed April 18, 2019, Proposed by #12739, Effective 3/19/2019, Expires 3/19/2029.