N.H. Code Admin. R. Env-Wq 1019.05

Current through Register No. 25, June 20, 2024
Section Env-Wq 1019.05 - Construction Requirements
(a) The permitted designer shall inspect the basal area preparation prior to fill placement, and shall submit an inspection report to the department's regional inspector at the time of final inspection.
(b) Compaction and smearing of infiltrative surface shall be avoided during fill placement and site preparation.
(c) The installer shall maintain 8 to 12 inches of fill between equipment tracks and the prepared surface.

N.H. Code Admin. R. Env-Wq 1019.05

(See Revision Note at chapter heading for Env-Wq 1000) #9086, eff 2-9-08

Amended by Volume XXXVI Number 41, Filed October 13, 2016, Proposed by #11184, Effective 10/1/2016, Expires 10/1/2026.