Section Env-Sw 2106.05 - Generic Work Plans; ContentA generic work plan for major non-emergency projects shall include:
(a) Name, mailing address, email address, daytime telephone number including area code, and credentials of the qualified individual who prepared the plan;(b) Name, mailing address, email address, and daytime telephone number including area code of the owner, qualified ADS contractor, utility company, public authority, or other entity or individual who will be authorized to use the work plan, if it is approved;(c) For work plans applicable to license-required work, and if known and different than (b), above, the name, mailing address, email address, daytime telephone number including area code, and ADS contractor identification information of the qualified ADS contractor who will be implementing the plan;(d) If known and different than (b) above, the name, mailing address, email address, daytime telephone number including area code, and ADS worker identification information of the qualified individual who will be in charge of the work conducted under the plan;(e) A description of the work to be undertaken, including:(1) The type and scope of work that the plan is designed to address, for example trenching for underground utility installation and repair, digging holes to install fencing or utility poles, excavating to construct foundations, retaining walls, or curbing, or placing capping materials over exposed asbestos;(2) The sequence of tasks, starting with site preparation pursuant to Env-Sw 2105.08 and ending with the site clearance determination required by Env-Sw 2105.15;(3) A description of the procedures and equipment to be used to control emissions during the excavation, storage, transport, and ultimate disposal of the asbestos waste, including the methods and procedures by which the work practices and engineering controls in Env-Sw 2105 will be met; and(4) The location of any temporary storage site and the final disposal site for asbestos excavated or otherwise removed from the site;(f) A description of how the site will be left following completion of the work, including related drawings of the capping system, including the replacement cover materials and supporting infrastructure in conformance with Env-Sw 2104.03;(g) Provisions for providing project commencement notice pursuant to Env-Sw 2105.07;(h) If the entity or individual named pursuant to (b), above, is not the owner, a statement indicating how the project records will be made available to the owner to facilitate compliance with RSA 141-E:23, I(d) and Env-Sw 2104.08(c);(i) A list and status of all other local, state, or federal permits and other approvals required to implement the plan, to the extent known;(j) A statement, signed by the qualified individual who prepared the plan, certifying that the plan meets all applicable local, state, and federal requirements for management of asbestos, including but not limited to the requirements listed in Env-Sw 2101.01(b), as applicable, and these rules; and(k) A statement, signed by the applicant certifying acceptance of the proposed work plan.N.H. Admin. Code § Env-Sw 2106.05
#7647, eff 2-16-02 (See Revision Note at chapter heading for Env-Sw 2100) (formerly Env-Wm 3906.05); ss by #9645, eff 2-16-10
Amended by Volume XXXVIII Number 37, Filed September 13, 2018, Proposed by #12605, Effective 9/1/2018, Expires 9/1/2028.