N.H. Code Admin. R. Env-A 4708.05

Current through Register No. 25, June 20, 2024
Section Env-A 4708.05 - Supplemental Information

The supplemental information required by Env-A 4704.02(e) shall include the following:

(a) The location and specifications of each building where the offset project actions will occur;
(b) The name, mailing address, electronic mail address, daytime telephone number, facsimile transmission number, and account number of each owner and each operator of each building, provided that if any owner or operator is the same as the project sponsor, the project sponsor's information may be cross-referenced;
(c) The name, mailing address, electronic mail address, daytime telephone number, facsimile transmission number, and account number of each person implementing the offset project, including each lead contractor, each subcontractor, and each consulting firm, provided that if any such person is the same as the project sponsor, the project sponsor's information may be cross-referenced;
(d) Specifications of equipment and materials to be installed as part of the offset project; and
(e) Building plans and offset project technical schematics, as applicable.

N.H. Code Admin. R. Env-A 4708.05

#9481, eff 5-23-09; ss by #10469, eff 1-1-14; (from Env-A 4708.06)