Section Env-A 1804.05 - Notification for Emergency Asbestos Abatement Projects

For emergency asbestos abatement projects, the O/O shall:

(a) Notify the department by telephone, fax, or email as specified in Env-A 1801.04(b) as early as possible prior to abatement or, if prior notice is not possible, within 24 hours of the beginning of each emergency asbestos abatement activity with information required under this part; and
(b) Provide written notification in accordance with this part to the department no later than 48 hours after beginning an emergency asbestos abatement.

N.H. Code Admin. R. Env-A 1804.05

(See Revision Note at chapter heading for Env-A 1800) #9298, eff 10-21-08

Amended by Volume XXXVII Number 19, Filed May 11, 2017, Proposed by #12172, Effective 5/5/2017, Expires 5/5/2027.