Section 618.954 - Project for the abatement of asbestos: Notification of Enforcement Section; fees
1. A contractor intending to engage in a project for the abatement of asbestos shall notify the Enforcement Section of the project on a form provided by the Enforcement Section.
2. The completed form must be received by the Enforcement Section at least 10 calendar days before any on-site work begins at the project.
3. The form must be accompanied by:
(a) A fee of $100 for a project which is greater than a project for spot repairs, but less than 260 linear feet or 160 square feet.
(b) A fee of $400 for a project which is greater than 260 linear feet or 160 square feet, but less than 2,600 linear feet or 1,600 square feet.
(c) A fee of $1,000 for a project which is greater than 2,600 linear feet or 1,600 square feet.
4. The owner of a building or structure will not be required to pay notification fees totaling more than $2,000 in any calendar year.
5. A form is not complete until the appropriate fee is received by the Enforcement Section. If an owner of a building or structure engages in any additional projects for the abatement of asbestos after paying a combined total of $2,000 in fees in any calendar year pursuant to this section, no additional fee is required for that additional project.

Nev. Admin. Code § 618.954

Added to NAC by Dep't of Industrial Relations, 12-19-89, eff. 1-1-90; A by R069-20A, eff. 4/11/2022