In determining the time permitted for compliance with an order for corrective action, as required to be stated in a written citation pursuant to NRS 477.240, the State Fire Marshal or the Board will determine the time for compliance with the order by considering, without limitation:
1. The accepted industry practice regarding the performance of the work necessary to comply with the order for corrective action, in the climate or weather conditions of the area in which the affected property is located. 2. The number of days during which the owner of the affected property will make the property available for the person to whom the administrative citation was issued to comply with the order for corrective action. 3. The time necessary to obtain materials required for the person to whom the administrative citation was issued to comply with the order for corrective action.Nev. Admin. Code § 477.981
Added by R124-13, eff. 6/26/2015