Nev. Admin. Code § 459.9947

Current through December 12, 2024
Section 459.9947 - Underground storage tanks: Duties of owner or operator required to implement secondary containment system

An owner or operator of an underground storage tank who is required to implement secondary containment for that underground storage tank pursuant to NAC 459.9945 and 459.9946 shall:

1. Notify the Division not less than 30 days before the installation or replacement of an underground storage tank and provide to the Division the proposed method of secondary containment planned for use; and
2. Upon request, make available for review by the Division records of the installation, testing and method of monitoring of the secondary containment.

Nev. Admin. Code § 459.9947

Added to NAC by Environmental Comm'n by R005-08, eff. 4-17-2008; A by R106-16A, eff. 11/2/2016
NRS 459.826, 459.830