If the holder of a permit or the Director finds that an injection well fails to demonstrate mechanical integrity during a test or a loss of mechanical integrity becomes evident during operation, the operation of the injection well must be stopped immediately and may not be resumed until approved by the Director.
Nev. Admin. Code § 445A.920
NRS 445A.425, 445A.465