Section 445A.66715 - Performance and inspection of work on water project; certification of substantial compliance with approved plans and specifications
1. Work on a water project must be:
(a) Performed in substantial compliance with the plans and specifications approved for the water project by the Division or the appropriate district board of health. Approval of the Division or the appropriate district board of health is required before carrying out any proposed changes in materials, equipment, quantities, configurations or processes, and before any additions or deletions of infrastructure, which would affect the quality or quantity of water.
(b) Inspected by qualified representatives of the supplier of water.
2. Within 30 days after the completion of a water project, the supplier of water shall certify to the Division or the appropriate district board of health that the water project was completed in substantial compliance with the plans and specifications approved for the water project by the Division or the appropriate district board of health.
3. Not later than 90 days after the completion of a water project, the supplier of water shall supply to the Division or the appropriate district board of health one set of drawings of the water project as it was built.

Nev. Admin. Code § 445A.66715

Added to NAC by Bd. of Health, eff. 2-20-97; A by Environmental Comm'n by R194-08, 10-27-2009; A by R104-22A, eff. 12/9/2022

NRS 445A.860