Nev. Admin. Code § 445A.6671

Current through August 29, 2024
Section 445A.6671 - Approval of water project: Prerequisites; effective period; revocation
1. The Division or the appropriate district board of health shall not approve a water project unless the application for approval of the water project demonstrates that the water project will comply with the applicable provisions of NAC 445A.65505 to 445A.6731, inclusive, and sections 2, 3 and 4 of this regulation.
2. Work on a water project must commence not later than 1 year after the water project is approved. The water project must be completed not later than 1 year after the date that work on the water project has commenced, except that the Division or the appropriate district board of health may extend this period in 1-year increments if:
(a) Work is being performed on the water project; and
(b) The Division or the appropriate district board of health receives a schedule of work and periodic updates on the progress of the water project.
3. The Division or the appropriate district board of health shall revoke its approval of a water project if work on the water project:
(a) Does not commence within 1 year after the approval of the water project becomes effective; or
(b) Ceases for a continuous period of 1 year.

Nev. Admin. Code § 445A.6671

Added to NAC by Bd. of Health, eff. 2-20-97; A by Environmental Comm'n by R194-08, 10-27-2009; A by R049-18A, eff. 8/21/2018
NRS 445A.860