Nev. Admin. Code § 445A.771

Current through December 12, 2024
Section 445A.771 - Examination of plans and specifications; submission of documents for review
1. An examination of the plans and specifications for a project must be performed to determine whether:
(a) The design is consistent with the facilities described in the facility plan;
(b) The proposed project, in concept, will meet discharge requirements; and
(c) The project will comply with applicable federal and state requirements.
2. An applicant shall submit the following documents for review:
(a) A design report.
(b) Except as otherwise provided in this paragraph, a set of specifications and plans not less than 90 percent complete. Depending upon the complexity of the project, a 50 percent submittal may be required.
(c) A final set of specifications and plans. These must be submitted before advertising for bids.
(d) Any addenda issued during the bidding process.

Nev. Admin. Code § 445A.771

Added to NAC by Environmental Comm'n, eff. 9-19-90; A by R115-10, 1-13-2011-Substituted in revision for NAC 445.42141

NRS 445A.135