Section 349.425 - Application by municipal obligor: Action by Board; processing by Director
1. The Board shall:
(a) Review an application submitted by a municipal obligor;
(b) Determine if the water project will preserve or increase the water available for beneficial use in the State; and
(c) Approve or disapprove the project in the manner provided in NAC 349.335, 349.340, 349.345 and 349.355.
2. If an application submitted by a municipal obligor is approved by the Board, the application will be processed by the Director in the manner provided in NAC 349.365 to 349.380, inclusive.