At the request of the National Board, of ASME, or of a boiler, pressure vessel or component parts manufacturer, the Department may conduct an inspection of a manufacturer's quality control program and facilities. This inspection shall be for the purpose of renewal of authorization to use the applicable non-nuclear ASME Certification Marks. Such requests shall be submitted to the Department at least six (6) months prior the expiration date of such Certification Marks. Initial quality control reviews shall be done by the ASME or an ASME designee. If the Chief Boiler Inspector is qualified as an ASME Review Team Leader to conduct non-nuclear ASME Joint Reviews, the Chief Boiler Inspector shall conduct all required reviews after the initial review for renewal of the non-nuclear ASME Certification Marks.
229 Neb. Admin. Code, ch. 10, § 003