Requirements upon completion of the permitted work - A duly authorized representative of the utility company shall certify in writing that all work has been done as per the approved permit. This certification shall be submitted immediately upon the completion of the work noting any significant variations from the original permit submittal. Failure to provide completion of work certification may result in the permit application being revoked. MDOT reserves the right to require the permittee to expose a facility as needed for inspection. Noncompliance with the approved permit shall require the utility company to remove the newly installed line and replace it in the permitted location. All costs associated with the relocation of the noncompliant facility shall be solely at the utility company's expense.
37 Miss. Code. R. § 1-7501-04001-1301