65-407-324 Me. Code R. § 4

Current through 2024-25, June 19, 2024
Section 407-324-4 - STANDARD FORMS
A.Applications and Agreements. Standard forms adopted by order of the Maine Public Utilities Commission shall be used for all interconnection applications, Interconnection Agreements, and feasibility, impact and facilities study agreements unless modified in accordance with this section. These standard forms will be available from the T&D Utility and posted on the Commission's website at www.maine.gov/mpuc. The approval of standard forms is delegated to the Director of Electric and Gas Utility Industries. If an Interconnection Customer or T&D Utility wishes to use an application or agreement that deviates from the standard form, the Interconnection Customer or T&D Utility shall submit the application or agreement to the Commission for approval. Approval of any deviation from the standard form is delegated to the Director of Electric and Gas Utility Industries.
B.Interconnection Application. Each T&D Utility shall allow applications to be submitted electronically and shall accept electronic signatures. The application form must include the following information and the standard form shall be designed to meet this purpose:
1. Basic information regarding the Applicant 2. Information regarding the type, size, location and other relevant specifications of the ICGF;
3. Information regarding the entity that will install the ICGF;
4. Certifications and agreements regarding utility access by the T&D Utility to the property on which the ICGF will be located, or documentation of Site Control for a Level 4 application;
5. Identification of the Licensed Professional Engineer that reviewed and approved the design of the Interconnection Customer- Generator facility, if applicable;
6. Other similar information as needed to determine the compliance of the Applicant with this Chapter.

65-407 C.M.R. ch. 324, § 4