Section 658-12-2 - Application Procedure
12.2.1Generally

Application for a permit must be made on a form supplied by the Board. The application must be accompanied by detailed plans, including a cross-sectional view, front and side elevations, and plot plans, and the fee set forth in Chapter 10 of the rules of the Office of Professional and Occupational Regulation. A permit must be obtained prior to commencement of the installation or alteration.

12.2.2Change in Tank Capacity, Piping or Operation

Any physical change that would increase the tank capacity or alter the piping or operation of the facility requires that a new application be filed, and a new permit be issued.

12.2.2.1 When any individual tank with a water capacity of 2,000 gallons or more is replaced, the following must be done:
1. If the facility has not been previously permitted, a new permit must be applied for and granted before the tank is replaced.
2. If the facility has been permitted, the Board must be informed in writing at least fifteen (15) days before the tank is replaced.