Current through October 23, 2024
Section 675 IAC 30-3-11 - Inspection reportsAuthority: IC 22-13-2-8
Affected: IC 22-15-6
Sec. 11.
(a) The first operating permit inspection of a boiler shall be reported on a form patterned after Form NB-5 set forth in Part 2 of the NBIC. Subsequent operating permit inspections of these objects shall be reported on a form patterned after Form NB-6 set forth in Part 2 of the NBIC.(b) The first operating permit inspection of an unfired pressure vessel shall be reported on a form patterned after Form NB-5 in Part 2 of the NBIC. Subsequent operating permit inspections of these objects shall be reported on a form patterned after Form NB-7 in Part 2 of the NBIC.(c) The inspection reports mentioned in subsections (a) and (b) shall be submitted to the division within thirty (30) days of the date of the inspection. The results of inspections shall be reported immediately to the division whenever a hazardous condition concerning a boiler or unfired pressure vessel is found to exist. Fire Prevention and Building Safety Commission; 675 IAC 30-3-11; filed Jan 5, 1996, 10:15 a.m.: 19 IR 1115; readopted filed Jul 9, 2001, 1:33 p.m.: 24 IR 3822; readopted filed Sep 21, 2007, 9:16 a.m.: 20071010-IR-680070389RFA; readopted filed Oct 19, 2007, 1:08 p.m.: 20071114-IR-680070389RFA; readopted filed Sep 5, 2013, 10:09 a.m.: 20131009-IR-680130182RFA; readopted filed 9/4/2019, 2:20 p.m.: 20191002-IR-675190336RFAFiled 4/28/2021, 11:03 a.m.: 20210526-IR-675200627FRA, eff 7/1/2021Transferred from the Boiler and Pressure Vessel Rules Board ( 680 IAC 2-3-11) to the Fire Prevention and Building Safety Commission ( 675 IAC 30-3-11) by P.L. 249-2019, SECTION 15, effective July 1, 2019.